Tottenham Court Road
RBG were engaged by Laing O’Rourke to peer review and certify numerous elements of their construction, primarily involving the temporary works and construction sequence for the Western Ticket Hall.
Subsequently, through the use of staged finite element analysis, RBG partially re-designed the prop removal sequence, adapted basement slabs for the addition of moling holes and the effects of the revised sequence, and designed new back-propping solutions.
Project Metrics
Project Value:
No Data
Year Completed:
No Data
Project Metrics:
No Data
Environmental Performance:
No Data
Sectors:
Rail
RBG Client:
Laing O’Rourke
End Client:
Laing O’Rourke
Architect(s):
No Data
Main Contractor:
No Data
RBG Services:
Construction Engineering